It has been a chilly month here at Frome Business Park, but this has not delayed the incredible work done by the team at Interaction. We're excited to see all the duct work going in, which will be exposed against the white beams to give a more industrial finish.
The roof has been completely resealed, insulated and painted ready for 600 windows to be installed. You can see below the progress shots that is happening in phases across the building
The windows on the sides of the building have all been going in, which match all the dark feature colours around the building.
In addition to this, we've also started works on our massive plant room. You can see the foundations coming together. This space will also double as the bike store and bin store for the entire building.
As we start to power through the build, we have been focusing on high-level tray work electrically and mechanically and the steelworks being painted.
Next steps will be to get in the raised access flooring so we can start to get in all the cables. Stay tuned for the next update.
Comments